Sewer Emergency 24/7

Call 864-277-4442

Current Projects

Current Construction Projects

 

Terra Pines Sewer Point Repair Project

This project consists of the construction of approximately 217 repairs to the existing 8-inch clay sanitary sewer mains and 6-inch clay lateral lines serving homes. Affected subdivisions within this project include:

Barrington Park, Baucom Park, Boiling Springs Fire Dept., Buena Vista Elem. School, Dayco Corporation, Dry Pocket Rd., Deerfield, Bennington Place, Chelsea Woods, East Greenville/Terra Pines, Grove Park Outfall Line, Hudson Corners Shopping Center, Marriot Hotel, Melrose, Parkway Sanitary Sewer Relocate, Parkway & Pelham Green, Riverbanks Energy Center, River Oaks, Spartan Place, Spinx Oil Company, Sugar Mill, Summer Crest Apartments, Sunbelt Industrial, Terra Woods, Thornblade

Construction began April 2017 and is scheduled to be completed by March 2018.

Aerial Stream Crossing Project

MetroConnects has identified multiple locations where drainage patterns and creeks have shifted exposing pipeline segments and supports for aerial crossings. Metro will install approximately 660 linear feet of new8-inch sanitary sewer pipe; concrete manholes and piers; and stream bank stabilization. As a result, this project will resolve the exposure of the sanitary sewer aerial stream crossings at several locations in Greenville County.

Construction began April 2017 and is projected to be completed by December 2017.

SCTAC Sewer Relocation Project        

Metro will relocate approximately 4,530 linear feet of 8-, 10-, and 12-inch sanitary sewer lines and install new precast concrete manholes within South Carolina Technology and Aviation Center (SCTAC) complex. The work will include the installation of trenchless crossings under SCDOT and Railroad right-of-ways, and the relocation of approximately 300 linear feet of varying diameter service laterals.

The project began June 2017 with a scheduled completion in February 2018.

Belmont-Augusta Sewer Point Repair Project

This project consisted of the construction of approximately 163 point repairs to Metropolitan’s 8-, 10-, and 12-inch clay sanitary sewer mains and associated service laterals located within County and State maintained public right-of-ways and Metropolitan sewer easements. The project focused within the Belmont-Augusta subdivision and began September 2016 was completed in August 2017.

 

Metro Connects

Contact

MetroConnects 120 Augusta Arbor Way Greenville, South Carolina 29605 864-277-4442 (t) 864-277-4272 (f) For Directions click HERE.